Metrolinx Finch West Light Rail Transit Project Map

Work Update - Week of March 16 - 20, 2020

Highway 27 Vicinity
  • Soil investigation continues on Highway 27
  • Installation of temporary traffic signals continue
  • Relocation of watermain pipes at Finch Avenue West - Highway 27 intersection continues
Highway 400 Bridge Rehabilitation
  • Construction of bridge decks in laydown areas
Finch West Station site
  • Crews are mobilizing to start pile driving activities at the site for the emergency exit of the underground station
  • Soil sampling activities and hydro vacuuming activities continue
Roadworks on Finch Avenue West
  • Road widening activities have extended to both sides of the roadway
  • Activities to relocate and/or protect utilities
Maintenance and Storage Facility (MSF)
  • Foundation work for the MSF site continues
Roadworks on Finch Avenue West
  • Road widening activities have extended to both sides of the roadway
  • Activities to relocate and/or protect utilities
Hwy 400 Bridge Rehabilitation Girder Installation

Highway 400 Bridge Rehabilitation girder installation.